      April 2017.
Company Inžinjering 1 d.o.o. Jelah in Bosnia and Herzegovina entrusted us the job of automating concrete factory. There was a need to improve the existing software in factory, and we automated the factory for the production of transportable concrete and concrete for the production of concrete products such as concrete panel holes, structural supports, etc.

inzinjering

 


      April 2017.
Company Prajo Beton d.o.o. From Virovitica again entrusted us the automation business. There was a need to improve the existing concrete software, and we automated the tower concrete for the production of transportable concrete.

prajo

 



      November 2016.
Company Kukec d.o.o. From Ivanić Grad again entrusted us with the job of automating factory. We automated concrete factory for the production of transportable concrete.

kukec

 



      November 2016.
We have automated another concrete factory in the company Nexe Beton located in Našice. In doing so, we have proven that our software is reliable and easy to use.

nasice

 



      November 2016.
Company HP-Invesrting d.o.o. From Mostar entrusted us the jub of automating a machine for the production of concrete products. After installing the software on the machine, we handled the employees of the fabric to work on the machine.

investing

 


      October 2016.
Binis d.o.o. From Banja Luka in Bosnia and Herzegovina wanted to increase quality in the production of concrete pavers. The aim was to equalize the quality of concrete needed to make the finishing layer of the pavers. For this reason, they hired us as a technologically unknown company in such a type of concrete production. With the help of a hygrometer and a new automaton, the customer has got a fully automated production of the finishing layer adapted to the most advanced color mix.

Betaplast

Betaplast

 

Betaplast

 


      September 2016.
Company Transport Beton Lubina d.o.o. In Knin, we have created a complete power and control cabinet on the fifth mobile concrete factory owned by this company. Complete electrical equipment developed in cooperation with SIEMENS. Also the concrete is equipped with a dispenser of additives of the our production assortment.

Betaplast

Betaplast

Betaplast

Betaplast

 


      May 2016.
Company Bossin d.o.o. From Mostar in Bosnia and Herzegovina has entrusted us with the job of automating part of the production process related to the storage and care of concrete slabs. The company is now able to track the product in the final stage of production and control the time it takes to dry the product itself.

Betaplast

      May 2016.


Company ALMY d.o.o. From Zenica in Bosnia and Herzegovina also entrusted us the job of automating own concrete. By the automation of concrete factory, they expanded their business as the company, so far they only worked in construction works.

Betaplast

      May 2016.

After the automation of concrete for the production of a fine layer in the production of concrete pavers for Betaplast we also automated another coarse concrete mixer. As such, Betaplast has automated the entire process of concrete flooring. We also set up dispenser additives from our production process.

Betaplast

      April 2016.


Automation of two concrete plants we finished a year ago for the company Ekogradnja Ltd. from Zrenjanin. The company Ekogradnja Ltd. is satisfied with the program for the production of concrete and are keen to modernize and set up the entire drive to pack concrete products. Pinky-s Ltd. has completed automation of machine for making concrete elements and processing plant for packaging. After more than two weeks of large machine modification and operation have been completed. All that remains is to inform workers with how to work with machine for making concrete elements and processing plant for packaging.

Stroj

pogon

 
 

      March 2016.

Automation of concrete plants to produce pavers and precast concrete elements for our existing users ABK Ltd. from Zapužane near Benkovac. Two concrete mixing plants small and large with 0.5 m3 and 1.00 m3 capacity have been completed. New probe for measuring humidity were set in both mixers. Earlier this year we set for this concrete plant Granumin, dosage device for granules.

Program

 
 

      February 2016.

Automation of concrete plants to produce pavers and precast concrete elements is completed for our new program user Kostic Ltd. from Čačak. Two concrete plants small and large with mixers 0.25m3 and 0.75m3 capacity has been completed. New probe for measuring humidity in both mixers are integrated and dosage device for granules (Granumin) is placed on small concrete plant.

Granumin

 
 

      December 2015.

The first concrete plant in Region which is fully automated and is on the board. Concrete plant has a mixer capacity of 0,375 m3, maximum capacity of all agregates on board is 80 m3, installed moisture probe for measuring humidity in agregate. The company Brodosplit Ltd. has produced a ship for the company Plovput Ltd. and in cooperation with Stav Ltd.from Zagreb they made a concrete plant on board. Ship concrete plant is designed to produce concrete in inaccessible places on the sea and for transport clean water to the islands.

Plovput

 
 

      December 2015.

Automation of concrete plant for company MIP Mostar Ltd. from Mostar in Bosnia and Herzegovina has been completed. Concrete plant has a mixer capacity of 1.5 m3.

Mostar

 
 

      December 2015.

Making automation and electrical wiring closet for tower concrete plant owned by Termobeton Ltd. from Breza in Bosnia and Herzegovina we have carried out on time. Concrete plant has a 3 moisture probes for measuring moisture in the aggregate, hot water boiler, 6 dispensers for additives, hydraulic valves on all outlets and have dosing belts for all aggregates with controlled speed. Concrete plant has a capacity of 1m3. The accuracy of dosing aggregates using belts is in one division on the scale.

Sarajevo

 
 

      November 2015.

Commissioning fourth concrete plant owned by Transport beton Lubina Ltd. from Knin passed quickly and without problems. Concrete plant was moved and placed in Ploče.

Ploče

 
 

      October 2015.

Quadro Company Ltd. has developed a machine for splitting concrete elements. The machine is entirely made and designed by the company Quadro Ltd. Pinky-s Ltd. has automated now two machines for the splitting of concrete elements (bricks, pavers, curb).

 
 

      October 2015.

The company Bolkop Ltd. from Slovenia has enabled us to create automation cabinets for mobile concrete mixing plant SBM Euromix 2000, which is located in Ptuj. Concrete plant has a mixer capacity of 2 m3. Measuring the moisture in the aggregate allows the plant to produce quality concrete.

Ptuj

 
 

      October 2015.

The company GPI Ltd. from Konjic in Bosnia and Herzegovina has entrusted us with their first concrete plant. The company is involved in the construction for two decades and wanted to expand its area of operations. Tower mixing plant has a mixer capacity of 1.5 m3. It has built-in three probe sets of Hydronix hydro probe. Concrete plant was moved from another location and there was a lot of work needed to be done. Hydro probe are set to work in automatic mode. Tower mixing plant has an aggregate silo and elevator. Water from the unit (boxes) is watershed down and hampers the customer (engineers) assessment of the moisture in the aggregates. For good concrete in concrete mixing tower hydro probe are needed in aggregate granulation 0-4 mm. Concrete plant has previously worked with the flow meter for adding water, but because of the production speed water balance was added.

Elevator

Konjic

 
 

      October 2015.

For the company ABK Ltd. from Zapužane near Benkovac we have mounted the device for dosage of pigments in granules called Granumin. The company ABK has been modernized with Granumin on existing concrete plant with their automation and we have set up dosage device for pigments in granules (Granumin). Granumin was entirely designed and manufactured in the company Pinky-s Ltd.

Benkovac

ABK

 
 

      August 2015.

In cooperation with Nexe Ltd. we have automated concrete plant owned by CD HIS Ltd. from Niš. Concrete Plant is currently at location Oraovačko polje (Grdelica) in the final part of constructing the highway row Belgrade - Macedonia. Concrete plant has a mixer capacity of 2 m3, recycler, heating boxes of aggregates and hygrometer in the aggregate. Commissioning of concrete plants has passed without any problems.

Niš

 
 

      May 2015.

Automation and cabling now fourth concrete plants owned by Transport beton Lubina Ltd. from Knin is in progress. Finishing works and commissioning will be at the end of the year. The company Transport beton Lubina has manufactured now the third mobile concrete mixing plant.

Knin

 
 

      May 2015.

For a company ATPR Knezevic is tailored program for the production of ready-mix concrete according to norm EN 206-1. The program enables automatic production of concrete for production of prefabricated concrete elements with the help of a hygrometer in a mixer.

Čačak

Čačak

 
 

      May 2015.

The company BAGERKOP Roberto Ltd. from Hrženica is our new customer. Installation of automation and commissioning has been completed without any problems and within the deadline.

 
 

      April 2015.

The company Prajo beton Ltd. from Virovitica has a concrete plant for production of prefabricated concrete elements. The plant has two concrete plants. Both concrete plants have Hydronix hygrometer. Making a good product has a need for the creation of good concrete. Our automation is using a hygrometer and making a concrete of the same consistency is much easier.

Virovitica

 
 

      April 2015.

The company Betaplast is constantly modernizing and now it's our regular byer. The company has entrusted us to build electrical cabinet, program, Granumin Easy (device for dosage of pigments in granules ) and wiring the entire plant. We've already created a automation for the automatic warehouse, machine for the manufacture of prefabricated concrete elements and finally concrete plant automation. Concrete plant is used for the production of prefabricated concrete elements.

Betonara

Granule

 
 

      April 2015.

The company Strešniki Golob Ltd. is from Mirna Pec in Slovenia and they exclusively have production of roof tiles. We have manufactured the energetics cabinet , Granumin Easy (device for dosage of pigments in granules) , wiring and software for them. Concrete plant has Hydronix hygrometer in a mixer. Production of roof tiles requires very accurate consistency of concrete so we had to fit hygrometer into our automation in the way that we always get the same concrete regardless of the moisture of each component.

Slovenija

Granule

 
 

      March 2015.

Ekogradnja Ltd. from Zrenjanin has a factory for the manufacture of prefabricated concrete elements. They have two concrete plants, smaller is 0.5 m3 capacity while bigger one has 0.75 m3 mixer capacity. Each concrete plant uses hygrometer because of easier and better production of quality concrete. Production of electrical cabinets, Granumin Easy (device for dosage of pigments in granules), software and commissioning of the plant was within the deadline.

Zrenjanin

Zrenjanin

 
 

      March 2015.

Company Međimurje PMP has entrusted us in changing their automation on concrete plant in Čakovec. Concrete plant serves for the production of prefabricated concrete elements and for making ready-mix concrete.

 
 

      December 2014.

The company Beton Lučko Ltd. from Zagreb entrusted us another concrete plant. Older automation in Karlovac with two concrete plants combined together one capacity 1.0 m3 and second 0.5 m3 was completed on time. The plant is used for production of prefabricated concrete elements. The dosing accuracy and consistency is critical for a good product. Installation of the radar hygrometer from Imko will improve quality of concrete products.

Karlovac

 
 

      November 2014.

For company ABK Ltd. from Zapužane near Benkovac we automated the process of stacking goods (grapple). The machine works fully with hydraulics. Precise positioning via laser and special hydraulic valves we made ABK Ltd. more competitive on market. Selecting multiple modes via touch screen and possibility of changing all settings the maintenance of the machine is minimal.

Grajfer

Grajfer

 
 

      September 2014.

Automation od concrete plant owned by D&M Bašić Ltd. from Imotski proceeded quickly and on time. At the end of training the operator and the firm are satisfied with our program. Our support for all users is current with two automation technicians.

Imotski

 
 

      September 2014.

Company Kamenolom Gorjak Ltd. from Krapina purchased a concrete plant in Zabok. Concrete plant has recycling water and hygrometer in aggregate. Kamenolom Gorjak Ltd. has entrusted to us their third concrete plant. The first concrete plant located in Krapina due to ravages of time but because of our good cooperation we will modernize their first concrete plant with our program.

Gorjak

 
 

     August 2014.

The company Unija beton Ltd. from Zagreb provided us with the opportunity to automate first concrete plant for them.

Unija beton

 
 

      August 2014.

ZKL - Zagreb Puppet Theatre is a new project for Pinky-s Ltd. This major project combines knowledge in automation, electrical equipment and comunications, numerous frequency converters (17) did not make our job easier. Development of software for the first time for theatre, enabling entry of new performances, hight limitations, speed, ability to manage all that on two different floors with Siemens hardware led to satisfaction of our new users.

Kazalište

Siemens

Siemens

 
 

      August 2014.

Put inženjering Ltd. from Niš, Serbia has need to automate one more concrete plant because of large amount of work they have and they have need for better quality of end user product. In order to improve the quality of making concrete we installed radar hygrometers from Imko GmbH in aggregate and mixer. Put inženjering manufactures concrete construction and "hallow panels" wich require exceptional accuracy in dosing all of components in concrete.

Niš

 
 

      June 2014.

Modern and future oriented company Put inženjering Ltd.from Niš, Serbia has entrusted us their first concrete plant. Good tehnical support has enabled us to automate plant within deadline.

Nis

 
 

      May 2014.

One more concrete plant owned by Nexe Group and manufactured by Merko CZ is automated. Plant is located in Bosnia and Herzegovina, Rogatica. Concrete plant is used for making mini hydro power plant in Rogatica.

Hydro_power_plant

 
 

      April 2014.

Due to increasing demand for various products firm Quadro Ltd. has a need for new or other techniques and technologies for the treatment of concrete pavement. The machine for hammers treatment of pavers.

Hammers_treatmant_machine

 
 

      April 2014.

The company Quadro Ltd. has need to improve speed, quality and support to easy facilitate new implementation of new ideas. We set up a Pinky-s program for easy access of all features connected with Siemens main unit (PLC) on mashine for making pavers and concrete blocks. The continuation of line machine for making pavers is self storage automated by Pinky-s Ltd.

Ame

 
 

      March 2014.

Concrete plant owned by Jarc cementni izdelki from Medvode, Slovenia is automated. Concrete plant has mixing capacity of 0.5 m3 and is put into operation within 4 days with minor changes in the electric wiring cabinet. Concrete plant is used to produce precast concrete products for the fine layer. In automation is included mixing concrete with a hygrometer in the mixer to automatically obtain the desired humidity of concrete. Pinky-s has made for a Jarc cementni izdelki company Granumin, the device for dosage of color in granules.

Granumin

Concrete_plant

 
 

      January 2014.

Concrete plant owned by Tempo-Vranica from Mostar is automated. Concrete plant is located in Odžak. Mixing concrete plant has capacity of 3.0 m3. Concrete plant is used in the preparation of objects on the European road corridor 5C. Concrete plant was put into operation with the wiring of the entire electrical cabinets, wiring the entire concrete plant and mechanicaly setting up concrete plant from scratch.

Road

Silo

From Scratch

 
 

      December 2013.

Concrete plant owned by Mucic & Co. Ltd. from Ljubuško is automated. Concrete plant has mixing capacity 2.35 m3 is put into operation within three days with minor changes in the electric wiring closet.

Mucić

pinky-s

 
 

      October 2013.

Concrete plant owned by Novotehna Ltd. from Rijeka is automated. Concrete plant has mixing capacity of 0.5 m3 it was put into operation in late October. Concrete plant has a new recycling unit.

Rijeka betonara

 
 

      September 2013.

Automation of mixing plant owned by Zidar Živanović Ltd. from Ugljevik is completed. Mobile mixing plant capacity of 0.5 m3 is automated and put into operation.

Teka

 
 

     September 2013

Automation of mixing plant owned by Katrapilar Ltd. from Bihac is completed. Liebherr mobile mixing plant capacity 0.5 m3 is automated and put into operation.

Liebherr

 
 

      August 2013.

Automation of 3'rd concrete mixing plant owned by Transport beton Lubina Ltd. in Šibenik is in progress. Finishing work and commissioning will be in mid-August.

Lubina

 
 

      July 2013.

New concrete plant in property of Presoflex Gradnja Ltd. from Požega is automated. Concrete plant has a system for water recycling and moisture probe for agregate.

Presoflex

 
 

      July 2013.

Pinky-s Ltd. manufactured machine for dosage of pigment granules, Granumin. Granumin has a maximum error of 10 grams in actual operating conditions, which is enough to meet the needs of any manufacturer of ready cast products.

Granumin

Granumin

 
 

      June 2013.

Automation of small mixing plant owned by Beton Lucko Ltd. in Jastrebarsko is completed. Production of colored concrete elements in the facility has required a need for a second concrete plant. Both mixing plants are associated with one PLC and computer.

Lucko

Lucko1

 
 

      May 2013.

Completed the automation of second concrete plant made and owned by firmTransport beton Lubina. Capacity of mixer is 1.00 m3. Concrete mobile mixing plant is located in Knin and is ready for commissioning at any location within 3 days. Company Transport beton Lubina again placed their confidence in automation by Pinky-s Ltd.

Lubina2

 
 

      April 2013.

Completed automation of Liebherr concrete plant from Nexe beton Ltd. Mixer capacity of plant is 2.25 m3. Nexe beton Ltd. in cooperation with firm Zidar Živković moved Liebherr concret plant to new location in Uglejvik, Bosnia and Hercegovina. Capacity of plant is up to 90 m3 of concrete per hour.

Concrete

Concrete plant

 
 

      December 2012.

Pinky-s Ltd. completed the automation of batching plant owned by Hering Inc. Široki Brijeg. The concrete plant is located in the village Studenci and is used for making concrete structures on the European road corridor 5C. The plant has a capacity to produce 1.5 m3 ready-mix concrete. The complexity of the system with Profibus modules is able to increase the potential of the concrete mixing plant. Concrete mixing plant was equipped with radar hygrometer SONO vario from IMKO GmbH, Germany.

Hering

Profibus

 

 

      November 2012.

Having finished automating the second shelf storage for Betaplast Ltd, we were asked to automate the entire production line for making pavers and concrete blocks. We have completed a revision of the automation and electrical closets of the entire production line. The new automation system enables the entire production line to be displayed on screen; we have reduced energy consumption and increased production capacity and product quality. Automation change has increased the reliability of the entire production line.

 

Omag

 
 

      October 2012.

We have signed a new contract with the Czech manufacturer of concrete plants Merko CZ, from Ostrava, regarding the automation of one of their concrete plants, capacity of 0.75m3, owned by Tehnika and their subcontractor INGRA, both from Zagreb. The particularity of this contract is the installation and commission of the concrete plant in an African country,  Algeria, for the first time. The installation and commission were completed on time.


merko

concrete

concrete

 
 

      September 2012.

Art forms are nothing new in the concrete industry; they are present in various buildings, cultural monuments, bridges, etc. Pinky-s donated colour pigments to the Museum of Modern Art in Zagreb.

 

art

art

 
 

     July 2012.

The automation of two concrete plants owned by Hren Ltd. D., Stubica has been completed. The larger concrete plant has a capacity to produce 1 m3 of ready-mix concrete and a smaller plant capacity to produce 0.5 m3 of concrete for precast industry. The software managing production of concrete is integrated with a supervisory-conrol system (dispatching system) and enables one to place orders from separate locations, view currently realized orders, as well as having an analysis review and insight into the warehousing.

 

Stubica

dispecer

 
 

     July 2012.

The second shelf storage automation for Betaplast Ltd., has been completed by Pinky-s Ltd. All the important information, sensors and alarms are displayed, as well as the occupancy of the entire warehouse.  Automation of the entire production line for pavers will begin in mid- September 2012.

 

betaplast2

 
 

     New !!!   Radar Hygrometers.

For more than a year Pinky-s Ltd. has been a distributor of Radar Hygrometers from IMKO, Germany, for the following countries: Croatia, Slovenia, Bosnia and Herzegovina, Serbia, Macedonia and Montenegro. Their accuracy and speed of response is sufficient for any application and harsh conditions in concrete plants.

Measuring the moisture in any industry: the concrete industry (aggregate or wet concrete), agriculture (soil, crops), wood industry (sawdust) with the new radar technology probes has no limits in their applications as their response time is in picoseconds and has an accuracy of below 0.5%.

 

sonomix

 
 

     May 2012.

Pinky-s Ltd. signed another contract with Betaplast Ltd. regarding the automation of shelf storage and the entire production line for pavers.

 
 

     April 2012.

Pinky-s Ltd. completed the automation of the concrete plant B1 owned by Zagroje TEHNOBETON. The program allows connection to the database from their laboratory on request. The current overview of the analysis in the laboratory allows better control of the concrete batching plant and the concrete.

 
 

     April 2012.

We signed a contract for the automation of the third concrete plant owned by IGMA Ltd.,  Koprivnica, NEXE group. The plant was automated in the shortest possible time. This contract confirms a good cooperation with the satisfied customer.

 

 
 

     February 2012.

We signed a new contract with the company "Zagorje Tehnobeton", Varaždin. regarding the reconstruction of automation of the concrete plant B1, Varaždin.

Special radar hygrometers for measuring moisture were re-incorporated in the project. Their response time is in picoseconds and the deviation of aggregate moisture is max. 0.5%, regardless of the type of aggregate. In addition there is no need for calibration of the probe.

 

 
 

     February 2012.

Pinky-s signed a contract with the company Betaplast Ltd. regarding the automation of the old warehouse. The old warehouse, where the mechanical flaws have been removed, has been turned into a modern technological solution that will pay for itself. The display on the computer gives instant access to the availability of shelf storage space. Using Siemens wireless technology has lowered the costs and facilitated an easier connection between computers and forklifts.

 

skladiste1

vilicar

 
 

      January 2012.

"NEXE BETON Ltd." has entrusted us to automate one more concrete mixing plant with the 0.5 m3 mixer. The concrete mixing plant is located in Đakovo. The capacity of the plant is 26 m3 / h.

 

Djakovo

 
 

      December 2011.

Automation of shelf storage completed for Quadro Ltd. Display on the computer gives an instant access to the availability of shelf storage space. Shelf storage automation has reduced the production costs.

 

quadro_vilicar

 
 

    September 2011.

Pinky-s signed a contract with the industry leader in the production of concrete constructions and ready-mix concrete, "Zagorje Tehnobeton d.d." The contract is related to the reconstruction of the automation of their third and the largest concrete plant in the surrounding area, "B2", Varaždin. B2 is the tower mixing plant with 2 mixers, mixing capacity of 2 x 2.25 m3. The plant is intended to produce ready-mix concrete and concrete constructions. After 2 months of preparation, commissioning will take place at the end of September.
The project includes special radar moisture probes. Their response time is in picoseconds and the deviation of aggregate moisture is max. 0.5%, regardless of the type of aggregate. In addition there is no need for calibration. The best equipment was chosen due to the complexity of the concrete plant and the importance of moisture probes in their production. To raise their quality to an even higher level, has once again been entrusted to the automation software of the company Pinky-s Ltd.

 

TehnoB2

 
 

    July 2011.

Pinky-s signed a contract with the Czech producer of concrete plants Merko CZ, Ostrava, regarding the automation of one of their concrete plants owned by RR Company in Zenica, Bosnia. The grand opening ceremony was held on 29.07.2011 and attended by high officials from BiH government and officials of Merko CZ.

 

zenica

 
 

    July 2011.

Pinky-s signed a contract with HIDROREGULACIJA d.d., Bjelovar regarding the implementation of automation in their concrete plant. The implementation of automation in their production has increased the quality of the products.

 

Hidroregulacija

 
 

    July 2011.

Pinky-S signed a contract with "NEXE BETON d.o.o., ASFALT I BETON PUT TUZLA”, Tuzla regarding the automation of the concrete plant made by Czech producer Merko CZ, Ostrava. By changing the automation system we have facilitated the work of operators and improved the quality of concrete.

 
 

    May 2011

The concrete mixing plant was moved and put into operation in Belgrade, Ostružnica according to the contract with "NEXE BETON Ltd. Belgrade". A mobile concrete mixing plant was set up in a very short period of time by "NEXE BETON Ltd.". The final wiring and installation of automation was completed in several days by Pinky-s Ltd. Upon rectifying some minor problems related to water at the concrete plant, the plant will be able to produce concrete at full capacity.

 

Ostruznica

 
 

    April 2011.

Pinky-s signed a new contract with one of the largest companies in the concrete industry "Zagorje Tehnobeton Inc." regarding the automation of their concrete plant "B5" in Hungary, Gyor. The plant is intended for supplying the concrete for building of the car manufacturer "Audi" factory. Our rapid implementation of the project once more proved our quality and showed that Pinky-s automation program can be chosen without hesitation.

 

TehnoB5

 
 

    March 2011.

Pinky- signed a contract regarding the reconstruction of the entire mixing plant "ZE-PROM Ltd." Sv. Ivan Zelina. The project will be finished by the end of the month.

 

Zelina

 
 

    March 2011

Pinky-s signed a contract with "NEXE BETON Ltd. Novi Sad" regarding the reconstruction of the mobile Liebherr mixing plant, capacity of 2.25 m3, in Ostružnica, Belgrade. The project will be finished in May 2011.


 
 

    March 2011.

Pinky-s signed a contract with one of the leading companies in the concrete industry "Zagorje Tehnobeton Inc." regarding the automation of one of their concrete plants "B3". Our rapid implementation of the project and the commissioning of the plant has been completed. The Pinky-s automation program has been installed and we are waiting for a quality software evaluation from our new customers.

 

Tehno1

 
 

     February 2011.

Pinky-s completed the commissioning of an automated plant with two batching plants for the production of precast products from "QUADRO Ltd". Using our software company "QUADRO d.o.o." has raised the level of quality and production speed of their products. "QUADRO d.o.o." made novelty in their manufacturing process, so we have embended that in our software and we perfected Pinky-s automation software.

Quadro

 
 

     January 2011.

The company "TRANSPORT BETON LUBINA Ltd." from Knin completed moving its own mobile mixing plant to Posedarje. Final works and commissioning is complete. Capacity of mixing was as expected ~ 50 m3 / h

Knin_Pinky-s

 
 

    October 2010.

Signed contract with "QUADRO Ltd." about making the whole energy cabinet, installation and automation of a facility for precast industry with two batching plants. Pinky-s Ltd. has developed a special "software" for two separate mixing plants on the same unit. Using our software company "Quadro Ltd." will further raise the quality and production speed of their products.

Two plants

 
 

    September 2010.

Automation and installation of the power cabinet for the second concrete mixing plant "KUKEC Ltd."  was completed on time. The installation in the business zone of Bjelovar is expected by the end of the year 2010, when all the works related to the plant is finished.

Power cabinet

 
 

    September 2010.

Pinky-s Ltd. completed the automation of the first contracted concrete plant "KUKEC Ltd.", Ivanić Grad. The mixing plant has a capacity of 1 m3 / cycle.

Otpremnica

 
 

    August 2010.

The company "TRANSPORT BETON LUBINA Ltd.”, Knin completed the construction of their first mobile concrete mixing plant, capacity of 1.5 m3 / cycle. Automation system by PINKY-S Ltd will increase the mixing plant capacity to up to 50 m3 / h. Its relocation and commissioning is expected by mid-October 2010.

 
 

     July 2010.

Pinky-s signed a contract with "GRAČEC Ltd." regarding the delivery of the "SUPERVISON AND CONTROL SYSTEM" which currently allows dislocated work of a concrete plant, but later is expected to develop one which will cater for a few plants. The concrete plant Gračec has had PINKY-S automation system for 3 years. The contract confirmed the customer satisfaction and our desire to develop new solutions that have a direct impact on business efficiency and concrete quality.


http://www.pinky-s.com/eng/automatika/nadzorni_sustav.html

 
 

     July 2010.

Pinky-s signed a contract with "KUKEC Ltd." regarding the wiring, manufacturing of the complete power cabinet and automation of the planetary mixing plant with a mixing capacity of 50 m3/h in the commercial zone of Bjelovar.

 
 

    19 May 2010.

We started with the installation of equipment in OPECO d.d. Virovitica needed for automation control of the concrete plant. The concrete plant is intended for production of concrete tiles. Pinky-s Ltd. built the complete power cabinet for the concrete mixing plant and pigment department

Opeco d.d. Virovitica

 
 

   14 May 2010.

Agreed reconstruction of Liebherr concrete plant, capacity 2.25 m3, owned by "NEXE BETON Ltd. NOVI SAD" , located in Beograd, Batajnički put.

automation Beograd

 
 

    7 April 2010.

A contract signed with "NEXE BETON Ltd." regarding automation of Liebherr mixing plant with mixer capacity of 2.25 m3 on location Lučko - Zagreb (former Hidrocommerce Ltd.)


liebherr

 
 

     25 March 2010.

A contract signed with "TRANSPORT BETON LUBINA Ltd." from Knin on automation of mobile ready-mix plant, capacity 50 m3 / h.

automatizacija

 
 

      January 2010.

In accordance with requirements of the profession certification of liquid pigment production to the standard HR EN 12878:2005 is currently being processed by the certification body IGH d.d.

tekući pigmenti

 
 

      January 2010.

A contract signed with the Czech producer of concrete Merko CZ, a.s. Ostrava on the reconstruction of the concrete plant owned by the GP BEST IZGRADNJA in Novi Sad.


best_izgradnja


 
 

      October 2009.

Team building is very important for a sound mind and a healthy body and the company values that. We regularly spend time involved in sports activities or having meals together. This is a bike ride to our lunch in a "Kaktus" restaurant located on one of the artificial lakes in Međimurje.

 


teambulding_1  teambulding_2

logo